Independent Project and FID Readiness Reviews
ROMAN Consulting Group, a Houston, Texas–based independent front-end capital project consultancy, provides independent project and FID readiness reviews for industrial capital projects. Owners, developers, boards and lenders use them to test whether the business case and project economics, scope, execution plan, cost estimate, schedule and risk are ready for a stage gate or final investment decision (FID).
In plain terms: a stage gate is a formal decision point between project phases; FID, also called sanction, is the point where the owner commits the full capital budget to build; and an independent gate review, or cold-eyes review, is a review by experienced people who had no role in developing the project. The service is part of ROMAN's Gate Reviews & Project Assurance practice, also known as independent project assurance.
Capital decisions carry the weight of every assumption made to get there. ROMAN's reviewers have spent their careers on the estimating and risk side of that equation, and have seen how often a project clears a stage gate on schedule momentum rather than genuine front-end loading (FEL) maturity. That background is what lets ROMAN challenge the numbers; ROMAN does not prepare the estimate it reviews.
QUICK ANSWER
Who provides independent FID readiness reviews?
ROMAN Consulting Group, an independent front-end consultancy based in Houston, Texas. Reviews are led by Roger Farish, PE, Managing Partner, who has more than 25 years of capital project leadership across LNG, refining, petrochemicals, gas processing, mining and power generation. ROMAN is a member of AACE International and the Construction Industry Institute (CII).
Starts
Within one week
Work begins within one week after the review scope is agreed.
Scope and fee agreed in a service order first
Findings
About one month at FID
Typical for larger, more complex projects. Smaller projects and earlier gates take less time.
Delivered before the gate
Led by
Roger Farish, PE
Managing Partner, supported by senior specialists from ROMAN's network, sized to the project.
More than 25 years of capital project leadership
Inputs
Your current project documents
Scope, business case and economic model, estimate and BOE, schedule, risk register, PDRI results and execution plan.
Full list below, under What we need from your team
What is an FID readiness review?
An FID readiness review is an independent check, made before formal project authorization or FID, of whether a capital project is ready for that decision.
It tests the business case and project economics, scope definition, execution plan, estimate maturity, schedule credibility and risk treatment the project needs to pass the gate.
ROMAN Consulting Group performs these reviews independently of the engineering and delivery teams, so findings reflect the project's actual readiness rather than internal advocacy for advancement. A clean result that confirms a project is ready is as useful as a gap caught early.

Front-end loading (FEL) is the planning phase of a capital project; the Construction Industry Institute (CII) calls the same phase front-end planning (FEP). It runs in three stages with a gate after each: FEL-1 (feasibility), FEL-2 (concept and scope development) and FEL-3 (definition).
FEL-3 usually includes front-end engineering design (FEED), and its gate is FID.
How does ROMAN run an independent FID readiness review?
ROMAN Consulting Group runs each independent FID readiness review in three steps and delivers the findings before the gate, while they can still shape the decision.
01
Readiness assessment
ROMAN evaluates whether project objectives align with business drivers and whether scope and technical assumptions are mature enough for the gate.
02
Risk and estimate alignment
ROMAN confirms that risks are identified and allocated appropriately, and that estimate maturity matches the level of capital being authorized.
03
Gap clarification
ROMAN surfaces residual definition gaps before they carry into execution, where they become far more expensive to resolve, and lists the actions the team can close.
Reviews are led by Roger Farish, PE, supported by senior specialists from ROMAN's network. On a review, ROMAN does not develop scope, prepare the estimate under review, or advocate for approval; our role is to clarify decision risk and strengthen the defensibility of the authorization itself.
What does an FID readiness review check?
An independent FID readiness review by ROMAN Consulting Group checks seven areas before the gate, anchored to AACE International Recommended Practices and Construction Industry Institute (CII) Best Practices:
01
Business case and project economics review
–
ROMAN tests whether the business case still holds at the project's current level of definition.
The review checks that the capital cost, schedule and key assumptions in the economic model match the estimate and schedule under review, and compares the project against the optimized "without project" scenario, so the decision rests on the project's real incremental value.
02
Estimate review
+
ROMAN reviews the cost estimate itself, separately from its basis.
The review checks that the AACE estimate class claimed matches scope maturity, from Class 5 (least defined) to Class 1 (most defined) under RP 18R-97, and that quantities, pricing, escalation, owner's costs and commissioning are in the estimate, not assumed.
Ratio checks and benchmarking, such as installation cost per dollar of equipment, test whether the totals hold up. ROMAN's reviewers build estimates in Aspen Capital Cost Estimator (ACCE), so they know how an estimate is put together line by line.
On one previous review, equipment counts did not agree across three project documents, and ROMAN concluded the estimate was one class less mature than the client assumed. See estimate review and validation.
03
Basis of estimate review
+
ROMAN tests the basis of estimate (BOE), the record of the scope, methods, data sources, assumptions, inclusions and exclusions behind a cost estimate.
A complete BOE lets the owner see what the number includes, what it leaves out and what would change it, so the estimate can be defended at the gate.
04
Schedule review
+
ROMAN reviews schedule logic, the critical path, long-lead procurement, and whether the schedule and estimate describe the same scope.
A schedule can pass every logic check and still be impossible to execute. On one brownfield review, the peak workforce had grown beyond what site parking and temporary facilities could support.
05
Contingency and quantitative risk analysis (P50/P80)
+
ROMAN tests whether contingency comes from quantified risk rather than a flat percentage, and whether the risk register reflects real conditions.
A quantitative risk analysis (QRA) uses Monte Carlo simulation to show the range of possible outcomes. P50 and P80 are the values with a 50% and an 80% chance of not being exceeded (AACE RP 40R-08 and 57R-09).
ROMAN consultants contribute to RP 57R-09 on integrated cost and schedule risk analysis (ICSRA). See Risk Management.
06
Scope maturity scoring (PDRI)
+
ROMAN scores scope maturity with the Project Definition Rating Index (PDRI), the CII method for measuring how well scope is defined before authorization.
PDRI rates 70 scope elements. On the traditional 1,000-point score, lower is better, and below 200 is the long-standing benchmark for FID readiness.
A facilitated PDRI 3 assessment in support of FID takes about two weeks in total. Read more: Project Definition Rating Index (PDRI) in Capital Projects.
07
Execution plan and contracting strategy
+
An execution strategy is only as credible as the engineering behind it.
ROMAN tests the contracting strategy, module and logistics assumptions, tie-in and shutdown planning for brownfield work, and whether phasing matches the schedule, workforce plan and estimate. ROMAN does not provide construction management, field controls or claims support.
Which review fits each FEL gate?
ROMAN Consulting Group matches the review to the gate. Earlier gates usually need a smaller, focused review; the full FID readiness review covers every area at the FEL-3 gate.
Gate 1
End of FEL-1
Is the opportunity worth developing?
AACE Class 5
PDRI 1 and a focused review, such as an estimate, schedule or business case review, scaled to the decision
Gate 2
End of FEL-2
Which concept goes forward?
AACE Class 4
PDRI 2 and a focused review, such as an estimate, schedule or business case review, scaled to the decision
Gate 3 / FID
End of FEL-3 and FEED
Is the defined project ready to sanction?
AACE Class 3
PDRI 3 and the full FID readiness review
Before construction mobilization
Optional follow-on
Is the project ready to be built?
n/a
CII Construction Readiness Assessment (CRA), as an optional follow-on
Typical AACE estimate class per RP 18R-97.
Who is an independent FID readiness review for?
ROMAN Consulting Group's independent FID readiness reviews are built for the people who must approve, fund or defend a capital project at a stage gate or FID.
Owners, developers and EPCs preparing for a stage-gate decision or final investment decision (FID).
PMO Directors, VPs of Projects and pre-FID Project Directors who need estimate and schedule credibility ahead of the next gate.
Capital committees, boards and investment committees (CEO, COO, CFO) requiring an independent view before authorizing funding.
Lenders and their technical advisors during lender review and technical due diligence.
Joint venture partners requiring an independent voice at the table before capital is committed.
Industries ROMAN supports
ROMAN Consulting Group supports owners, developers, EPCs and OEMs on industrial capital projects in:
That includes brownfield expansions and revamps at operating refineries and petrochemical plants, covered below.
When should you bring in an independent review?
TIMING
Engage at least two months before the decision meeting
Start early enough to finish the review before the gate and leave time to close findings. At FID the review itself takes about one month, so engage ROMAN Consulting Group at least two months before the decision meeting.
Before final investment decision.
Before an FEL-2 or FEL-3 (FEED) gate, when the estimate class may not match the level of definition.
Before the FEL-1 gate on larger, more complex projects.
When an estimate is going to a board for approval, or needs independent validation for a lender or funding application.
During lender technical due diligence.
After cost growth between phases or an internal governance audit finding.
For new or emerging technology with no cost history.
When the owner lacks in-house estimating, risk or PMO capacity.
What deliverables do you get?
ROMAN Consulting Group delivers a single, clear written report tailored to the project's scope and to the specific gate or FID decision, combining qualitative and quantitative validation. The report covers:
Business case
Whether the project economics hold at the current definition, against the optimized "without project" scenario.
Risk and findings
Risk and contingency assessment, with a summary of findings and recommendations.
Scope and plan
Scope alignment and execution assumptions, with PDRI and CRA scoring where in scope.
Actions
A list of actions the project team can close before the gate.
Schedule and cost
Schedule health and executability, estimate basis, methodology, ratio checks and estimate class.
Readiness conclusion
Go, conditional go with the conditions to proceed, or not yet ready.
Each review is a single written deliverable on one project, not a retainer. Optional follow-ons: a CII Construction Readiness Assessment (CRA) before mobilization, and periodic independent oversight for high-risk projects moving into execution.
What decision-makers gain
An independent FID readiness review gives the capital committee, board and lenders:
A clear, defensible decision basis for real-world uncertainty.
Stronger defensibility of the capital authorization decision.
Greater confidence from executives, boards and lenders.
Reduced likelihood of re-baselining or late-stage scope change.
Improved capital predictability across the portfolio.
What we need from your team
To start, ROMAN asks for:
Project scope of work
Project business case and economic model
Cost estimate (current version)
Basis of estimate (BOE)
Project schedule
Risk register
PDRI results, or the FEL deliverables list if no PDRI has been run
Execution plan and contracting strategy
The gate criteria the project will be judged against
Who leads your review?
Roger Farish, PE, Managing Partner of ROMAN Consulting Group, leads ROMAN's independent FID readiness reviews.
He has more than 25 years of leadership experience on complex capital projects across LNG, refining, petrochemicals, gas processing, mining and power generation, in senior and executive roles at Fluor, Bechtel, Kiewit and Linde. At Kiewit he led the company-wide implementation of Aspen Capital Cost Estimator (ACCE).
Credentials: licensed Professional Engineer (PE); MBA, University of Chicago Booth School of Business; BS and MS in Mechanical Engineering, Tulane University.
Professional activity: AACE International at the national level and in the Houston Gulf Coast Section; Construction Industry Institute (CII); Engineering and Construction Contracting (ECC) Association.
Recent speaking: "Mastering Advanced Capital Cost Estimates with ACCE," OPTIMIZE 26, AspenTech user conference, Houston, May 2026.
Supported by: senior consultants from ROMAN's network, including contributors to the AACE Recommended Practices ROMAN applies.
Case study: an independent pre-FID review that held FID until the project was ready
ROMAN Consulting Group's independent pre-FID review gave one owner team the basis to hold FID until the project was ready.
What decision-makers gain
CASE AT A GLANCE
Project: New industrial facility, owner-assembled project team
Gate: Final investment decision (FID)
What ROMAN reviewed: Scope and readiness; execution plan, contracting and workforce assumptions; schedule credibility and executability; estimate maturity and basis of estimate; risk and contingency
Finding: Scope, schedule and estimate maturity were not yet where they needed to be for FID
Outcome: The owners held FID for six months; the project has since reached FID
The owner team asked ROMAN for an independent review before taking the project to FID. ROMAN found that scope, schedule and estimate maturity were not yet where they needed to be.
The owners used the findings to hold FID for six months while the team closed the gaps, and the project has since reached FID.
An independent review is worth most when it says a project is not ready yet.
Brownfield and revamp reviews for refinery and petrochemical projects
ROMAN Consulting Group's independent FID readiness reviews also cover brownfield expansions, conversions and revamps at operating refineries and petrochemical plants, where projects inherit the constraints of the site around them.
Tie-ins to operating units bring shutdown (turnaround) windows, interfaces and live-plant constraints. Construction beside active sites competes for access, laydown and logistics, and schedule pressure to reach FID can leave assumptions untested.
Simultaneous operations (SIMOPS), demolition and unknown site conditions add further cost and schedule risk. ROMAN checks that the estimate, schedule and risk register carry these risks explicitly before FID.
SECOND CASE AT A GLANCE
Project: Brownfield refinery conversion
Stage: FEL-2, AACE Class 4 estimate
What ROMAN checked: Ratio checks, such as installation cost per dollar of equipment and pipe quantity per item, against typical brownfield ranges; the risk content of the estimate basis
Findings: Both ratios fell below typical brownfield ranges and pointed to likely understatement, a pattern a bottom-line review would have missed. Construction indirects, weather impacts and tie-in complexity were only thinly addressed.
Why it matters: On a brownfield project, these are the categories most likely to erode the budget
Frequently asked questions about independent FID readiness reviews
These answers cover questions owners and lenders often ask ROMAN Consulting Group that the sections above do not.
Does ROMAN replace our internal project team?
–
No. ROMAN Consulting Group reviews independently of the engineering and delivery teams and does not develop scope or prepare the estimate it reviews. The review clarifies risk and readiness and lists the actions the team can close; the project team retains ownership of the work itself.
What drives the cost of an independent FID readiness review?
+
ROMAN Consulting Group scopes and prices each review as a single written deliverable on one project, not a retainer or a program-level commitment. Cost depends on project size and complexity, the number of review areas in scope, how ready the documents are and the time left before the gate. Fees are agreed in a service order before work starts.
How is an FID readiness review different from due diligence or benchmarking?
+
An FID readiness review by ROMAN Consulting Group tests whether scope, estimate, schedule and risk maturity justify passing a gate, usually for the owner's own governance. Project due diligence verifies technical, commercial and permitting assumptions, often for a lender or investor. Database benchmarking compares a project with historical metrics; ROMAN uses benchmarking as one check inside a hands-on review.