FEL Scope Definition (PDRI)
ROMAN Consulting Group, a Houston, Texas–based independent front-end capital project consultancy, facilitates PDRI assessments for industrial capital projects. Owners, developers and EPCs use them to measure how well a project's scope is defined, and to close the gaps before a stage gate or the final investment decision (FID).
In plain terms: the Project Definition Rating Index (PDRI) is the Construction Industry Institute (CII) method for scoring scope definition during front-end planning. A facilitated workshop rates each scope element and turns a subjective discussion into a score and a list of gaps.
Independent facilitation keeps the score honest. ROMAN has no stake in whether the project advances, so the score reflects the project's actual definition, not the team's confidence in it.
QUICK ANSWER
Who facilitates independent PDRI assessments?
ROMAN Consulting Group, an independent front-end consultancy based in Houston, Texas, and a member company of the Construction Industry Institute (CII), which developed PDRI. Assessments are led by Roger Farish, PE, Managing Partner, who facilitates PDRI assessments for owners.
Starts
Within one week
Work begins within one week after the scope is agreed.
Scope and fee agreed in a service order first
Duration
About two weeks
Total time for a facilitated PDRI 3 assessment in support of FID.
Pre-scoring, workshop and report
Method
CII PDRI
PDRI for Industrial Projects: 70 scope elements, rated in a facilitated workshop.
PDRI MATRS where in scope
Led by
Roger Farish, PE
Managing Partner, supported by senior specialists from ROMAN's network, sized to the project.
More than 25 years of capital project leadership
What is a PDRI assessment?
A PDRI assessment is a structured scoring of how completely a capital project's scope is defined, using CII's Project Definition Rating Index.
PDRI for Industrial Projects rates 70 scope elements across three sections: Basis of Project Decision, Basis of Design and Execution Approach. Each element is rated 0 (not applicable) or from 1 (complete definition) to 5 (incomplete or poorly defined). CII's building and infrastructure versions use different element counts.
On the traditional weighted 1,000-point score, lower is better, and below 200 is CII's long-standing threshold for authorization, which for most owners is FID. CII's current versions also report maturity ratings, where higher is better.

Front-end loading (FEL) is the planning phase of a capital project; the Construction Industry Institute (CII) calls the same phase front-end planning (FEP). It runs in three stages with a gate after each: FEL-1 (feasibility), FEL-2 (concept and scope development) and FEL-3 (definition).
How does ROMAN facilitate a PDRI assessment?
ROMAN Consulting Group runs each PDRI assessment in four steps.
01
Pre-score
ROMAN reviews the project documents and pre-scores the PDRI, so the team arrives at the workshop with the project already understood.
02
Facilitate
Owner, engineering, licensor, contractor and operations representatives rate each scope element together, with ROMAN as the independent facilitator.
03
Score the gaps
ROMAN scores every element and records the gap behind each poorly defined one, in the team's own words.
04
Close the actions
The team receives a scored report and a list of actions it can close before the gate.
PDRI assessments are part of ROMAN's Gate Reviews and Project Assurance service. They are led by Roger Farish, PE; ROMAN facilitates and scores, and does not develop the scope being scored.
What does a PDRI assessment check?
A PDRI assessment by ROMAN Consulting Group follows CII's published PDRI method and templates, matched to the project type.
01
Basis of Project Decision
–
Whether business objectives, capacity, products, technology and site are defined and agreed.
Gaps here, such as unsettled capacity and yield assumptions, flow into every later deliverable and every estimate built on them.
02
Basis of Design
+
Whether process and engineering design criteria, equipment lists and layouts are recorded in approved deliverables.
ROMAN tests whether scope is documented and reconciled, not just whether it exists somewhere. Design criteria held in working files rather than approved documents count as gaps.
03
Execution Approach
+
Whether the procurement strategy, contracting plan, schedule, commissioning responsibilities and startup requirements are defined.
These elements are often the last to mature. Gaps left open at authorization can become delays and change orders in execution.
04
PDRI MATRS
+
Where in scope, ROMAN applies PDRI MATRS (Maturity and Accuracy Total Rating System). It adds accuracy factors that test the planning environment, such as leadership, team, resources and process, alongside the maturity of the deliverables.
The result tells the owner whether the score itself can be trusted.
05
Scope maturity and estimate class
+
A PDRI score shows whether the scope can support the estimate class being claimed.
ROMAN flags when an estimate is presented as Class 3 on scope that only supports Class 4, so the gap is seen before capital is committed. An independent estimate review can then test the number itself.
06
The right PDRI version
+
CII publishes PDRI versions for different project types, including industrial, building and infrastructure projects.
ROMAN uses the version that matches the project, so the elements and weights fit the work being scored.
Which PDRI fits each FEL gate?
ROMAN Consulting Group matches the PDRI to the gate. Running it at least twice, early and before authorization, shows whether the gaps are closing.
Gate 1
End of FEL-1
Is the opportunity worth developing?
PDRI 1
An early score that shows where definition is thinnest, while gaps are still cheap to close.
Gate 2
End of FEL-2
Which concept goes forward?
PDRI 2
Tests whether the selected concept is defined well enough to enter FEL-3 and FEED.
Gate 3 / FID
End of FEL-3 and FEED
Is the defined project ready to sanction?
PDRI 3
Confirms scope completeness before authorization. About two weeks in total in support of FID.
CII also provides an interim assessment, PDRI 2i, between Gate 2 and Gate 3.
Who is a PDRI assessment for?
ROMAN Consulting Group's PDRI assessments serve teams that need an objective measure of scope before a gate.
Owners and EPCs preparing to move a project from FEL-1 to FEL-2, or from FEL-2 to FEL-3.
Project directors who want an objective, facilitated score instead of an internal self-assessment.
Capital committees that require documented scope maturity scoring before a gate decision.
Organizations building PDRI into their stage-gate governance for the first time.
Industries ROMAN supports
ROMAN Consulting Group supports owners, developers, EPCs and OEMs on industrial capital projects in:
When should you run a PDRI assessment?
TIMING
Score early, then again before authorization
Run PDRI at least twice: early in FEL-1 or FEL-2 to find gaps while they are cheap to close, and again at the end of FEL-3 to confirm scope completeness before FID.
Before each FEL gate, matched to PDRI 1, 2 or 3.
Before FID, to confirm scope completeness.
When an estimate class is claimed that the scope may not support.
When the owner, engineer and licensor do not agree on what is in scope.
When a project restarts after a pause and the team has changed.
What deliverables do you get?
ROMAN Consulting Group delivers a scored PDRI report the team can act on before the gate:
PDRI score
The overall and section scores, and how they compare with the readiness benchmark.
Actions
A list of actions the team can close before the gate, with suggested owners.
Element ratings
A rating for every scope element, with the reason behind each poorly defined one.
MATRS results
Accuracy factors on the planning environment, where PDRI MATRS is in scope.
Gap list
The specific gaps to close, grouped by section.
Each assessment is a single written deliverable on one project, not a retainer. When both are in scope, PDRI 3 results feed ROMAN's independent FID readiness review.
What decision-makers gain
A facilitated PDRI assessment gives the capital committee and project team:
Objective evidence of scope maturity in place of subjective confidence.
One shared view of scope across owner, engineering, licensor and operations.
Lower risk of change orders and rework carried into execution.
A documented basis for whether the estimate class matches the scope.
What we need from your team
To start, ROMAN asks for:
Project scope of work and design basis
Process flow diagrams, P&IDs and equipment list, as available
Plot plan and layout drawings
Execution plan, procurement and contracting strategy
Project schedule
Any earlier PDRI results
Workshop participants from owner, engineering, licensor, contractor and operations
Who leads your PDRI assessment?
Roger Farish, PE, Managing Partner of ROMAN Consulting Group, facilitates ROMAN's PDRI assessments.
He has more than 25 years of leadership experience on complex capital projects across LNG, refining, petrochemicals, gas processing, mining and power generation, in senior and executive roles at Fluor, Bechtel, Kiewit and Linde. At Kiewit he led the company-wide implementation of Aspen Capital Cost Estimator (ACCE).
Credentials: licensed Professional Engineer (PE); MBA, University of Chicago Booth School of Business; BS and MS in Mechanical Engineering, Tulane University.
Professional activity: AACE International at the national level and in the Houston Gulf Coast Section; Construction Industry Institute (CII); Engineering and Construction Contracting (ECC) Association.
Recent speaking: "Mastering Advanced Capital Cost Estimates with ACCE," OPTIMIZE 26, AspenTech user conference, Houston, May 2026.
Supported by: senior consultants from ROMAN's network, including contributors to the AACE Recommended Practices ROMAN applies.
How is PDRI different from CRA and an independent project review?
The three answer different questions at different points on the timeline. PDRI asks whether the scope is defined, at Gates 1 to 3.
CII's Construction Readiness Assessment (CRA) asks whether the project is ready to be built. It scores 228 readiness factors in 15 categories against CII industry data before mobilization. A project can be well defined and still not be ready to be built.
An independent FID readiness review asks whether the whole package, including business case, scope, execution plan, cost, schedule and risk, is credible enough for the decision. A good PDRI score is one input to that review, not a substitute for it.
The three answer different questions at different points on the timeline. PDRI asks whether the scope is defined, at Gates 1 to 3.
CII's Construction Readiness Assessment (CRA) asks whether the project is ready to be built. It scores 228 readiness factors in 15 categories against CII industry data before mobilization. A project can be well defined and still not be ready to be built.
An independent FID readiness review asks whether the whole package, including business case, scope, execution plan, cost, schedule and risk, is credible enough for the decision. A good PDRI score is one input to that review, not a substitute for it.
Frequently asked questions about PDRI assessments
These answers cover questions owners often ask ROMAN Consulting Group that the sections above do not.
Who should attend a PDRI workshop?
–
The people who own the scope: owner project leadership, engineering, the licensor where there is one, contractors and operations. ROMAN Consulting Group facilitates and scores. Having every party in the room is what turns the score into shared agreement on the gaps and who closes them.
Can our team run PDRI internally?
+
Yes. CII publishes the method, and many owners self-assess. An independent facilitator from ROMAN Consulting Group keeps the ratings objective, challenges optimistic scores and brings experience from other projects, which matters most at the gates where the score supports a funding decision.
What drives the cost of a PDRI assessment?
+
ROMAN Consulting Group prices each assessment as a single written deliverable on one project. Cost depends on the PDRI version, the size and complexity of the project, the number of participants and whether PDRI MATRS is in scope. Fees are agreed in a service order before work starts.